The eight figures that decide the door you actually need, in the order they should be settled, and what happens when one of them is estimated instead of.
Specifying a rigid high-speed door means fixing eight parameters before an order is placed: clear opening, headroom, wind class, cycle duty, temperature separation, safety devices, control interfaces and service access. Each one constrains the others, so they are settled in sequence rather than collected as a list.
The clear opening is the finished structural aperture, not the distance between the old door frames. On a retrofit the existing guides often hide a rough opening that is out of square, and the door has to be sized to the structure that will carry it.
Every rigid construction parks its leaf above the opening. The envelope needed depends on the guide geometry, and it must be checked against sprinkler branches, lighting, cable trays and crane rails. A header zone that looks clear on a drawing often has a service running through it.
The wind class is a property of the building elevation and its exposure, and it is expressed through EN 12424. It is not a function of the door type, and it cannot be inferred from a neighbouring opening that faces a different direction.
The number of cycles per day sets the drive rating, the brake size and the maintenance interval. A week of controller data during peak production is the useful input; an annual average hides the peak that actually wears the door out.
Where the door separates two temperatures, the specification states the temperature difference, the humidity condition on each side and whether condensate has a drainage path. Those three facts decide whether heated guides, a thermal break and a drainable threshold are needed.
The safety arrangement follows the traffic, not the door size. A pedestrian route crossing the opening needs presence detection beyond a closing timer; a vehicle-only opening needs coverage of the swept area and a monitored bottom edge.
The door controller has to accept signals from the equipment around it: conveyors, airlocks, dock levellers, traffic lights, access control. The interlock sequence is written down, because it is the part that gets lost when a controller is replaced.
Access to the guides, the drive and the header determines how long a repair takes. A door installed behind a fixed rack or above a mezzanine is a door that will be serviced late.
| Parameter | Typical source of error | Consequence |
|---|---|---|
| Clear opening | Measured to old frames | Door does not fit the structural aperture |
| Headroom | Services not surveyed | Guide or box clashes with sprinklers or ducts |
| Wind class | Copied from another elevation | Leaf deflects or seals lift in storm conditions |
| Cycle duty | Nominal catalogue figure used | Drive and brake wear out early |
| Temperature | Difference not stated | Condensation and ice at guides and threshold |
| Safety | Photocells only | Pedestrian or pallet not detected in the swept area |
| Interlocks | Verbal agreement with process supplier | Conflicting commands, damaged leaf |
| Access | Racking installed after the door | Long stoppages for routine service |
Each of the eight parameters has a natural owner, and the specification fails when ownership is unclear. The clear opening and headroom come from the building survey. The wind class comes from the structural or façade engineer. The cycle duty comes from the operations team, from logged data. The temperature and humidity condition comes from the process design. Safety devices and interlocks are agreed between the door supplier and the process supplier. Service access belongs to maintenance.
Writing the owner against each line in the door schedule turns a wish list into a set of decisions that someone has accepted responsibility for. It also shows immediately which parameters are still assumptions, which is usually where the rework comes from.
The following pages cover the adjacent decisions in the same product family, so the specification can be reviewed end to end.
The table lists the references that normally change the selected configuration. It is a specification checklist, not a certification statement for any particular installation; the applicable class is confirmed against the measured opening and the site conditions.
| Reference | What has to be confirmed |
|---|---|
| EN 13241 | Product standard the specification is written against |
| EN 12424 | Wind class for the elevation |
| EN 12426 | Air permeability to be declared |
| EN 12428 | Thermal transmittance where temperature separation applies |
| EN 12453 | Safety in use of the power-operated door |
The measured clear opening and the available headroom, because they eliminate constructions before any performance discussion starts.
It can be estimated, but it should be confirmed from controller logs. Traffic usually peaks above the average derived from output figures.
Only where the internal opening can be pressurized by external conditions, for example behind an open external bay. A true internal partition does not need a wind class.
The eight parameters with their measured or confirmed values, the selected construction, the safety arrangement, the interlock sequence and the commissioned settings.